Claudius Crozet's Comparative Estimate of the Five Lowest Bids Offered for Blue Ridge Tunnel No. 1, January 21, 1850
Claudius Crozet offers the Board of Public Works his assessment of the bids for one section of the Tunnel project.
Comparative Estimate of the five lowest bids offered for the Blue ridge tunnel No. 1 Jany. 21st, 1805
Quantities of Work | Jno. I W. Rutter. | Richard Fox. | John Kelly & Co. | Jonas H. More | G. B. Manby. | Remarks. |
Tunnel. | prices | Amounts | prices | Amounts | prices | Amounts | prices | Amounts | prices | Amounts |
| $ | cts | $ | cts | $ | cts | $ | cts | $ | cts | $ | cts | $ | cts | $ | cts | $ | cts | $ | cts |
Excavation, 46,500 C. yards | 3 | 15 | 146,475 | 00 | 3 | 24 | 150,660 | 00 | 3 | 50 | 162,750 | 00 | 3 | 85 | 179,025 | 00 | 3 | 90 | 181,350 | 00 |
Arching at portals 57 M. bricks | 14 | 00 | 798 | 00 | 11 | 00 | 627 | 00 | 11 | 00 | 627 | 00 | 12 | 00 | 684 | 00 | 11 | 60 | 661 | 20 |
Packing over arches 75 C. yards | | 70 | 52 | 50 | 2 | 00 | 150 | 00 | | 80 | 60 | 00 | 1 | 75 | 131 | 25 | | 90 | 67 | 50 |
Cut masonry of portals 220 C. yards | 5 | 00 | 1100 | 00 | 12 | 00 | 2640 | 00 | 10 | 00 | 2200 | 00 | 8 | 50 | 1870 | 00 | 8 | 75 | 1925 | 00 |
2 Drains Concrete 100 " | 5 | 00 | 500 | 00 | 3 | 00 | 300 | 00 | 1 | 25 | 125 | 00 | 7 | 00 | 700 | 00 | 2 | 25 | 225 | 00 |
Paving 100 Sq. yards | | 75 | 75 | 00 | 3 | 50 | 350 | 00 | 1 | 50 | 150 | 00 | 2 | 00 | 200 | 00 | 1 | 80 | 180 | 00 |
Total Amounts of Tunnel | $149,000 | 50 | $154,727 | 00 | $165,912 | 00 | $182,610 | 25 | $184,408 | 70 |
Excavation Stony ground 12,000 yds | | 38 | 4560 | 00 | | 25 | 3,000 | 00 | | 25 | 3,000 | 00 | | 35 | 4,200 | 00 | | | | | |
Rock 12,000 " | | 90 | 10,800 | 00 | | 65 | 7,800 | 00 | | 85 | 10,200 | 00 | 1 | 50 | 18,000 | 00 | | 87½ | 21,000 | 00 | |
Extra hauling 10,000 yds 5 hundred ft | | 01 | 500 | 00 | | 04 | 2,000 | 00 | | 02 | 1,000 | 00 | | | 01 | 500 | 00 | | 03 | 1,500 | 00 | |
do. 50,000 yds 3 " " | 01 | 1,500 | 00 | | 04 | 6,000 | 00 | | 02 | 3,000 | 00 | | 1,500 | 00 | | 03 | 4,500 | 00 | |
Walling, dry 480 cubic yards | 2 | 10 | 1,008 | 00 | 1 | 95 | 888 | 00 | 1 | 65 | 792 | 00 | | 25 | x 120 | 00 | 1 | 37½ | 660 | 00 | |
" for 2 cowpits 40 " | 2 | 10 | 84 | 00 | 1 | 95 | 74 | 00 | 1 | 65 | 68 | 00 | | 25 | x 10 | 00 | 1 | 37½ | 55 | 00 | x doubtful prices |
" Rockwork 216 " | 3 | 60 | 777 | 60 | 2 | 45 | 529 | 20 | 1 | 65 | 356 | 40 | | 75 | x 162 | 00 | 5 | 12½ | 1,107 | 00 | |
Riprapping 11,400 C yds | | 40 | 4,560 | 00 | | 75 | 8,550 | 00 | | 50 | 5,700 | 00 | | 8,550 | 00 | | 75 | 8,550 | 00 | |
Turning the road, about 1/8 of a mile. | | | 50 | 00 | | | 50 | 00 | | | 50 | 00 | | | 50 | 00 | | | 50 | 00 | |
Clearing and Grubbing 1½ acre | 40 | 00 | 60 | 00 | 20 | 00 | 30 | 00 | 50 | 00 | 75 | 00 | 1 | 50 | x 2 | 25 | 30 | 00 | 45 | 00 | |
Total amounts of Approaches | $23,899 | 60 | $28,921 | 20 | $24,241 | 40 | $33,094 | 25 | $37,467 | 00 | |
Total Estimates without Arching | $172,900 | 10 | $183,648 | 20 | $190,153 | 40 | $215,704 | 50 | $221,875 | 70 | |
From all appearances the excavation will probably consist chiefly of compact sandstone; so that very little interference will be experienced from water and no arching will be necessary: it may nevertheless be proper to introduce this element into the comparison of the Bids. The following statement exhibits the influence of this circumstance on the bids, under the supposition that one half of the Tunnel will require arching with brick.
Rutter had not the confidence of the Board having already failed to comply with [?] Fox also had not the confidence of the Bo. Had been [?] a partner of Rutter
Additional Excavation 4,700 c. yards | 3 | 15 | 14,805 | 00 | 3 | 24 | 15,228 | 00 | 3 | 50 | 16,450 | 00 | 3 | 85 | 18,095 | 00 | 3 | 90 | 18,330 | 00 |
Arch 1,400 M. bricks | 11 | 75 | 17,155 | 00 | 12 | 50 | 18,250 | 00 | 13 | 00 | 18,980 | 00 | 18,250 | 00 | 12 | 00 | 17,520 | 00 |
Packing 2,000 c. yds | | 70 | 1,400 | 00 | 2 | 00 | 4,000 | 00 | 80 | 1,600 | 00 | 3,500 | 00 | 90 | 1,800 | 00 |
Total Amounts for Arching | $33,360 | 00 | $37,478 | 00 | $37,030 | 00 | $39,845 | 00 | $37,650 | 00 |
Aggregates including Arching | $206,260 | 10 | $221,126 | 20 | $227,183 | 40 | $255,549 | 00 | $259,525 | 70 |
C. Crozet
Eng. B. R. R. R.